 So I promised to show ya'll a few photos of some actual work I have done around here.  I was never really enthused about the idea of painting this bar wall, so when it hit me to sheath it in pallet wood I jumped on that. Allen had been scrounging pallets for me for months and I had stripped a lot of them down to usable wood where they were just waiting for finishing.  So, I finally bit the bullet and sanded, stained, painted, sanded again, and patched for two days to get enough planks to do these 2 walls.  I didn't make a lot of effort to hide any patches, dents, or bangs in the wood.  I mean, it's obviously pallet wood and obviously reclaimed, so there's the "charm".  Ha! Anyway, I thought it came out rather well.  The corners are done in 1 1/2" angle iron and these make helluva good corner guards..  The iron is just stuck on for now because I'll have to take it back off and cut to fit when I run the finish floor and baseboard.  In person it looks better.  The color is a bit washed out in this photo because, due to low light in the warm months in my house, I have a devil of a time getting decent photos.  I often have to use a flash and it just doesn't look right.

 This photo is a little better but it's a little washed out too.  Anyways....I finished this counter top and back splash and wanted to run a little of the glass tile just to see how that was going to look.  I'm very pleased with this but please note; the tile has not been grouted yet, so it will look a little different when finished.  This gives me a lot of motivation to keep going.  I'm very anxious to get the kitchen finished because I think it's really going to be awesome.

 However, I had to take a break from all that and take advantage of the fact we are in an extended drought.  I have needed to fix this basement wall for years after I discovered just how much rain floods down the mountainside during the winter rains.  If the rest of the house were built this area would remain dry but.....we all know that has not happened yet so....I have to treat this as if it is forever an exterior wall.  Which meant chopping the bottom 2 feet off of the wood framing, forming a 4 inch thick wall and pouring it in concrete.  Here you can see the girls inspecting my forms.  It came out real well.  I even played around and did a faux board formed look on the outside.  This 11 foot section is a little less than half of what I need to pour but it's the worst part of the problem.  I admit I should have done this to begin with..but I did not realize the amount of water etc. around here.  And I was under the supreme delusion that the rest of the house would come along soon enough. Ha!!
Anyways, this form has been dropped, the wall sheathed back, and also insulated and covered on the inside.  Snug as a bug!  I'm now running multiple shelves on the inside in an effort to better organize the basement and my studio there.  I'll rub the exterior of the concrete here, below grade, to produce a smoother finish, then waterproof heavily and backfill.  There is still no sign of any rain anywhere in our near future so I shouldn't have any issues finishing this in the dry.

I also thought I'd take advantage of the drought in other ways!  We have ample dried foliage, leaves, flowers, grass and any things else you can think of here, so I gathered up a armful of stuff, a couple handfuls of feathers via some molting chickens and threw together this autumnal wreath.  Not too shabby I guess.  Certainly was cost effective.  haha!

Monday, January 26, 2015

Something's Cooking In The Kitchen


I suppose a more accurate title would be Something's Curing In The Kitchen, but this'll do!  Unbelievably enough I finally got up the gumption to start pouring the first of the kitchen counter tops.  We had a whole week of spring-like weather and I just couldn't let that pass without doing some kind of house work.  A lot of times the hardest part of a project is simply starting, so I just took one step at a time and pretty soon it was going!  The nice weather made getting and hauling the sand and gravel enjoyable and easy and that was one of the biggest steps.
Now, in this first photo you can see that I have everything pretty much ready and in the next photos I'll give you some detail shots and more explanations.  As you can probably guess, the plastic sheeting is to protect my cabinets and also the stove that I left in place for the pour.


I ran my forms on grade, which is to say, I set the top of the form at the height I wanted my finished counter top.  To me, it's just so much easier to finish to the top edge of the form rather than try to make a grade line and keep it visible while you are pouring.  Of course, that's not that hard and what I had to do anyway on the sides that butted the backsplash area.  When I get my forms set to the right elevation I always mark it with a crow's foot and that allows you to see if something happens to knock your form up or down.


I then leveled my grade line across the back and around the sides and was pleased to see that when I measured up 2" inches in random spots it actually hit the grade line! ha!  I also partially ran a few long screws into a few studs to help "lock in" the counter top slab.  It would probably never move on it's on but expansion and contraction and all that jazz, you know.


There are several ways to do the edge form and I choose again, just to clamp mine to my cabinets with a 1" spacer between the cabinet and the vertical form, which is the standard counter top overhang.  Clamping does sometimes cause the form to roll out a little at the top but I'll show you how I remedied that in a minute.


The ends of the form were screwed off to available surfaces.  I always use screws also because they are much easier to remove than nails and will not pull out like a nail will.  Of course, there was very little pressure against this form but 2 inches of mud will exert a little.


This is looking at the inside of the edge form and you can see I caulked everything really good.  The concrete mixture will weep way more than you might think so I always caulk any crack really well.  A nice, smooth bead of CLEAR caulk in the bottom inside edge will give the bottom front edge of the concrete a really smooth finish too.  I know everything looks white but this is that caulk that goes on white but dries to clear.  The edge form and spacer are white though.  To the left you can see the 3/4" plywood that tops my cabinets and is the bottom form for the counter tops.


The very last step is to put in your reinforcing and in this case I used dog wire.  It's a 4"x2" grid wire.  You could use chicken wire, hardware cloth or even #3 rebar.  You also want your wire to end up about halfway up in the concrete rather than mashed down against the plywood.  An easy way to do this is to initially pour a blob of mud about every 12 or 16" and then pull the wire back up so that it's about an inch off the bottom.  I'm pouring 2" counter tops, btw.  The mud will hold the wire in place then as you pour the rest.


We mixed the concrete outside and then just brought it in with buckets.  I float the mud down as I go, pushing the concrete on grade towards the back first and working your way towards the front form.  With floating you are kinda pushing and patting and smoothing.  Not trying to get a smooth finish yet, just trying to get everything on grade.  I also vibrate the edges with a palm sander and tap the underside of the form with a hammer to compact the mud.  When bubbles stop coming to the surface you know you are done.  Don't vibrate any more or you can actually separate your mix too much.
In this photo you can also see two other tricks.  The side form against the stove is not nailed off as this was not possible without moving the stove and all that crap.  I pushed the stove over to the left as much as I could and slid in the edge form.  I then placed the wooden wedges every few inches and tapped them down until I got a good snug fit.  Once it's screwed to the front edge form and caulked good it's not going anywhere.  Always use wood wedges too because they won't scratch or dent anything. 
You also see 2 wires running over the slab.  I anchored 2 tapcons into the studs of that wall and then wired 2 little turnbuckles in the wiring, which ran over to the front edge form.  As you tighten (or loosen) the turnbuckles you can move the form in or out, however you want.  Works great.  I simply used a straight edge on the front edge to determine when it was good.  These are a tiny version of the large turnbuckles we use on big wall forms and such.  After you pour and get it floated down, you want to check your lining again and make sure nothing moved.

Okay!!  So, any questions??  I hope I explained all that correctly.  If I didn't, please let me know and I can address it in the next posts.  I'll do another on troweling the concrete for a good finish, removing the forms and all that.

Wednesday, May 15, 2013

Back In The Mud


I finally got the hearth poured under my gas fireplace so I thought I'd show ya'll a quick post on how I did the forms.  It's fairly simple really.  The top of the 2x4's are the permanent framing that will hold up the slab.  That strip of darker plywood on the outside is the edge form that will drop down from under the concrete once it has cured.  The whitish looking board is the side of the edge form that will drop off later also.


Here you may be able to see a little better.  The bottom edge form is basically 2 pieces of 3/4" plywood screwed together at a right angle and then screwed to the framing.  I wedged it in places to get the flat part level.  After that was on I screwed the edge form on.  All of these pieces were ripped to the correct widths so I could use the edges as grade.  Am I explaining this right?  Everything that was to come off later was also oiled so it would release easily.


I found a new mix for doing the slabs and counter tops and I am very pleased with it.  It is one part Portland cement, 2 parts aggregate (89-10 in this case) and 3 parts sand.  That seemed like a lot of sand to me but it works fine and finishes wonderfully.
I bent a #3 piece of rebar to go round the outer edge and then filled in the inside with some wire mesh and chicken wire.  Whatever ya got just make sure to pull it up in the mix and not let it get trapped on the bottom.


I also used a clear silicone caulk to seal all the cracks because a fair amount of water is going to weep out of a slab.  As you screed and trowel it down, some slurry will come over the edge so I put some old crappy towels down to catch my mess.  Of course, it helps that I don't have finish floors down now to protect.  I put a fan on this from both sides to kinda help the water evaporate.  A pool will form on the top after you float the slab down flat and you don't want to start working it until that disappears or you'll just work the water back down into the concrete.  As the water evaporates you can see the surface start to tighten up and then you can start with a slick trowel.  One or two passes and then let it rest to tighten up a little more.  And repeat until you get the surface you want.  Well, it's harder than that but I can only explain to a point; it's something that you just have to see and try.
I have wrecked the edge form off at this point and am going to smooth the corners and seal it before too long.  Hopefully.  Then I can start running the slate tile!!!  Yay!!
Allen and I also finished installing the pendant light in the kitchen and they look fantastic!!  I'll show that soon.

Saturday, September 03, 2011

Hard Bargain

Well, I had good intentions (but you know what they say about that) for my posting while I was away but ran into a couple of issues. First, the place where I'm staying has horrible Internet connection. I'm using a wireless connection but can only sometimes get a strong enough signal to stay online more than a few minutes. I inquired about the hotel's connection but they want $10 a week for it and I said screw that. I would get an excellent signal at work but do not have time to even log on, much less write anything and I'm not about to hang around after work to blog. Sorry folks. Don't mean I don't care about you! But that shower, however crappy it is, is calling to me mightily by quitting time. Hopefully, I can figure out a solution to this dilemma but in the mean time if I am slow answering emails or replying to comments, that is why. Also, and just as significantly, this first week kicked my ass, to be honest and I really didn't have the energy to do much writing. We worked overtime everyday except Friday and by the time I got back to my room, cleaned up and got something to eat, I was about ready to pass out. My crew has been working on hanging brick angle and so must work out of man lifts up to 80 or so feet in the air. Of course, we must wear safety harnesses that add about 6-7 lbs. to what you're already carrying and in the blazing sun with hardhats on. We've been going in at 6:00 a.m. to get some coolness but that makes for some early nights. At least for me. I can't stay up all night like I used to could. Fortunately, as far as the stress of the work, I do see a light at the end of the tunnel. The first part of the week was rough, to say the least, but by Thursday I was feeling like I was starting to get acclimated to it all again and Friday was almost enjoyable. Maybe that was partially due to the fact I knew we were leaving at 2:30 but I felt not quite so wore out. It was still about 100 degrees that day and I burnt the living crap out of myself cutting some steel but it wasn't a bad day. (The slag spewed back on me because I was cutting against concrete and it basically showered me completely in molten steel.) That statement may help you understand just how bad Monday through Wednesday was.
When I was pondering what to blog about I was thinking about just how hard it is to describe what we go through on these jobs to someone who has never experienced it. I mean, I picked metal BB's (basically) out of my flesh and yes, it hit in some very sensitive areas for a woman, but it was still a fairly enjoyable day, comparatively. Not to sound overly dramatic but it occurred to me; nothing I have ever done while building my house has ever been as hard as what I do at work. And my house includes quite a bit of structural steel and concrete. I admit, the spring box was close and some days at work are super easy but it is just a whole 'nother world there. I think that is part of the reason I get so pissed off when I hear people speak disparagingly of construction workers or have some office slackers make snide remarks to us. It kills me that society has so much respect for doctors and professors etc. but the people that build the structures for these esteemed members of society to work in are treated like so much trash, for the most part.
Well, that's enough ranting for now! Thankfully they are letting us have a 3-day weekend for the holiday so I will probably have some time to post again before I go back. I will try to write about something other than work also!

Oh, I forgot to mention, the photo is the view from the front of the job but you can only see one of the two tower cranes. Directly beneath the crane is some of the forms they use for pouring the floors. These are some interesting contraptions as they can be jacked up or down and shoved out over the edge to extend the floor they are forming. After the floor is poured, these forms are dropped down and pulled out by the crane to be replaced with shoring. The shoring is the 4x4 posts and scaffolding you see to the far left. There will be a forest of these posts amongst the floors. These must be left in place for a few weeks until the concrete samples taken from these pours break at the prescribed strength.
And...if you're wondering why I wasn't wearing some type of protection when I got burned...well, that's a good question. I just didn't take the time to get down from the lift and go get my sleeves. I only needed to wallow this hole in the steel out about an 1/8th of an inch and knew it wouldn't take a minute. So, in an effort to save time I did it bare armed. I eventually had to burn a few more, so I did retrieve my leathers when I went down to doctor myself. And yes, Daddy Rabbit chewed my ass when he found out that I had injured myself, so now I'm sore on both ends. Ha!

Wednesday, June 22, 2011

Distant Early Warning

The photo here does not directly relate to what this post is about but is more of just an example to make my point about something. Now, I don't want this post to come off as pissy or elitist or some other such; it's just my thoughts on some stuff that has bothered me for a while. Of course, I know I'm preaching to the choir, so to speak, on this subject because all of my readers are smart and savvy enough to know what I'm fixin' to tell you but just in case....
Over the years of blogging I have come across a number of other blogs on building, as you would expect. Mostly it's regular people building their own home or barns or such. And that is great. Ya'll know that I try to encourage everyone to try their hand at building, especially women, for a variety on reasons. And in the course of reading some of these blogs I have noticed some of them have quite a few readers. Unfortunately, it seems that the blogs of people who are least qualified to be showing other people how to build something are sometimes the most heavily read. Let me just say, just because someone is being adventuresome in their construction; say, building in some exotic location, does NOT mean they know what they are doing. Now, some of these are fun to read regardless and I am not promoting myself as some all-time expert; I make mistakes too, which I will also show you. That said, I do have almost 20 years of construction and safety training and with that I say please, PLEASE, be very careful who you take construction advise from and what their qualifications are. I don't care how much experience they say they have in concrete, if they don't know what a snap-tie or a johnny clamp is, you run from them, quickly. They are an idiot and have never worked in the industry. In fact, we used to have a game we played when I worked construction. We often had fellows drop by our jobs looking for work and they often claimed to be form carpenters or whatever. This is common in commercial construction. Now, they wouldn't have a resume or anything but would just tell the super what their experience etc. Now, if they promoted themselves as super-carpenter, one who had done all and been all, and even if he uttered the famous words of one guy, "when it gets too rough for everybody else, it's just right for me", we, the crew, would immediately start taking bets on how fast this guy was going to drag up. Not, IF he was going to drag up but just how fast, because when people start talking like that they are full of shit. We never were wrong about a one. Keep that in mind when reading these blogs.
I have also noticed that many of the self-sufficiency types and all really like to get out of the city limits where there are fewer, if any, restrictions on building. Now, I don't have a problem with this. I'm only in the county and didn't have inspections on my house BUT, it is still built to code. Now, I agree that many times the building codes are stupid about some things and the city just wants the revenue. However, for the most part these building codes are for your protection. They are there so that JimBob doesn't put your rafters on 3 foot centers and have the ceiling or roof collapse on you. It's there so your neighbor isn't shitting in a 55-gallon drum and having it overflow onto your property. It's there so your well-meaning cousin doesn't burn your house down because he really didn't know how to wire that junction box anyway.
I have seen some of the stupidest things done, by way of building, on some of these blogs. I have seen people frame a two story house and not put the first header over a door or window. That's fine until about 2 years down the road when things have sagged so bad they can't open any of the doors or windows. I have seen a lot of unsupported spans on outer floor bands and rafters; no piers but in the corners. Code will tell you how far you can span according to the size lumber. I actually saw a couple install rafters with the wide side down. Now, I don't know how anyone can look at that, no matter their experience or lack thereof, and think,' yeah, that's the way those go'.
Granted it was just a chicken coop (a big one) but, holy hell! how do you do something like that.?? I have seen people install roofing in about every bad way imaginable. Granted now, roofing can be difficult and you really need to have help if you don't know what you are doing.
And Lord O' mercy, don't get me started about people pouring concrete. Concrete is a wonderful and versatile medium. It is astounding in it's strength and beauty. Under the right circumstances, it will kill you deader'n a hammer in seconds if you make one mistake. Concrete is not something to screw with and you especially need to watch who you get your advice from. Now, it's hard to make a deadly mistake pouring a slab for a patio or such but you can mess up and waste an enormous amount of money if nothing else. The photo above is of some formwork from one of my old jobs. We were pouring foundation piers and footings that were 2-3 feet deep. You can see some of the massive amount of rebar that went in those footings and the steel sticking up was just part of what was stubbed up for the walls that would pour on top. And, in all honesty, these were kinda wimpy footings for commercial work. I've seen one guy, on a blog, pour walls where he only put a stick of rebar every 4 or 5 feet and then claimed that was overdoing it. And NO, fiber in the mix does not help on walls. Fiber is to help keep slabs and walkways from cracking. It is NOT structural. Nothing over his doorways, windows etc. Please, please, please, consult with an actual concrete professional if you are going to pour walls, even some retaining walls. Walls must be tied into the footings correctly and with sufficient steel and the footings themselves must be sufficient to hold the wall up. Now, I know footings for a house are nowhere near what commercial construction calls for but, as I have actually seen, a 2-inch thick little spread footing is NOT going to hold up a two story house, especially when it was poured right on top of the topsoil! They didn't even dig down past the frost line or to substantial enough earth to meet resistance from a probe. You can get into a lot of trouble with concrete in a hurry if it is done incorrectly. The form itself can fail, which I have seen, and that can hurt or kill someone. Concrete (reinforced) weighs around 140 lbs. per cubic FOOT. That means one yard is way over 3,000 pounds. Concrete is expensive nowadays and hard to get back out once it has set! If you screw it up it can be costly to repair.
It just pains me to no end to watch people install such piss-poor foundations for their houses and such and you know, come a year or two or 5, everything is going to be so damn outta whack the walls are going to be cracking and all kinds of hell. The foundations, however they are done, must be done correctly or the rest of the house will suffer for it. And you too, I might add.
So, this is my rant. Just please, take most of what you see online with a grain of salt. Even me. For one thing, I have come to realize that something that is code down here might not be advisable in another climate and some stuff I've seen done up north (because it was code) I would never do here. MUCH depends on your climate, the geology of your region and the building materials you are using. Please, please be aware of these things, research your ideas for your region and know and go by the building codes, even if you don't have to.

Wednesday, March 23, 2011

Smooth Operator

I am very, very tired tonight but I did want to get up a few photos of what we have been working on in regards to the ongoing chicken coop saga. I tried to get some mud yesterday but they were too busy so we had to set up for today. This morning it was threatening rain but I didn't want to reschedule; didn't know when things would be dry again. So, I kept it coming and turns out it didn't rain at all. It was, at least, nice and cloudy so we were not having to work in the hot sun. Here my help was taking pictures instead of pulling that mud down! Ha!
Seriously, there wasn't much time for picture taking so the next chance was as I began to finish the stuff. The large float there is called a bull float. You push and pull it across to smooth the surface and then move over to the perpendicular side to cross over your strokes. This works down any high spots and helps level the mud before you float it off by hand.

Obviously, the bull float is great when you are pouring an area larger than you can reach from the sides. After the mud has set some you can put a knee board out on the wet concrete, to distribute your weight, and kneel on it to reach the center.

And here you can see a little of the footing for the tool shed. We really worked hard because they sent me a little extra concrete. I ordered 2 yards but the plant loaded around 2 1/2 yards or maybe even a little more. The driver had a yard and a half left over from one pour and they added another yard to make sure I had enough. We poured everything I could think of. We filled concrete block around the house, set one fence post, dumped some on where the floor of the tool shed is going to be and finally the driver just dumped the rest on one part of my driveway that is bad to wash. That is another reason I like to order from a plant if I can; you will often get a little more than what you order. I figured it to be around 1 1/2 yards but you can't order a half a yard, so I went with 2. The driver was real nice and suggested the driveway thing because he said he would hate to take it back to dump on the plant yard when I could use it somewhere.

This is the finished slab. Or at least, finished after I decided I had had enough. Actually, it is quite slick and I was pleased with the results. My left hand may not function tomorrow, but I got a pretty finish. A friend commented that the chickens were not going to care what the slab looked like but of course, you all know that is not the point with me. Yes, I am screwed in the head. I care what it looks like but a slick finish is much easier to clean. I said those damn chickens better care!! They better ooh and aah over it and rub their little feathers over it and compliment me weekly on their beautiful digs.
I'm not sure if I mentioned in my other post but the slab is slanted 1/4" per foot to one side so that water will easier drain off after cleaning.
Well, bedtime for me!! and gonna take it kinda easy tomorrow.

Friday, March 18, 2011

Progress

I piddled around yesterday enough to get the forms lined (straightened), the vapor barrier in and started on the rebar. I think I've mentioned this before but a vapor barrier underneath concrete is very important if there is ever going to be any enclosed structure on top of the concrete. If you don't have it you can get sweating on top of the slab and, inside a structure, this is not good. Also, I always put my stakes and kickers about every 3 to 4 feet down the form. Any further apart and you tend to get bows in the form. If I were using actual beamsides or forms (plywood backed by 2x4's) I would not need kickers on such a short form. Always kick both sides of all corners too. I used the turnbuckles for my kickers because, 1. I had them and didn't have 2x's and 2. the form had a little wiggle to it so I could pull it out with the turnbuckles.
I just scrounged out what #4 rebar I had and threw that in there. I think it's on about 16" centers. This slab really didn't need much but you do want to have some steel in any slab or sidewalk. Heavy wire mesh would have been fine also. I'm hoping to pour Monday or Tuesday.

The flowers are really kicking in here. Things are real starting to grow and blossom.

The broccoli has gone gangbusters! I picked a large mess for supper the other night and it continues to produce these shoots just all over the plant. I am curious to see how long they will do this. I guess until it gets pretty warm. And so far, knock on wood, I've not had any problems with pests.

Thursday, March 17, 2011

Forming

Ed was correct in his assumption that I would be pouring concrete soon. This is the formwork for the future chicken coop. Or the Taj MaCoop, as Woody put it. Now, I know some of you are looking at this and thinking, that's a helluva thick slab for a chicken coop. Well, it's not so much. See, none of my land is flat. None. Not 10 square feet anywhere. It's all gently rolling hills or steep inclines. I picked the flattest part I could find around the garden but it still meant a 12 inch elevation change in 12 feet. But, that is easily remedied with a concrete slab.
I wanted it connected to the garden for a variety of reasons. At certain times, when there are no tomatoes, the chickens can be let right into the garden to patrol for bugs etc. Scraps from the garden are easily thrown to the chickens and chicken poop is easily gathered and taken over to the garden. Plus, I already have electricity and water at the garden and it won't take much to trench the power down to the coop, although I would like to maybe install some solar lights. And, last but not least, I already have shock wire run around the garden and it won't take much to incorporate the coop with this. The coop will also be known as ChickenTraz.

So, forming the slab here wasn't much problem but I did have to fill the interior in order to have only a 3 inch thick slab to pour. This involved wheelbarrowing a lot of dirt and gravel but that's good exercise. However, if you do this, you MUST tamp the fill so that it won't collapse on you later and have your slab crack. And that dirt will settle, I assure you. So, that is what this contraption is above; a motorized tamp. One of those little handle doolollies ain't going to do it. These big tamps are way cool. Due to Allen and I being in the business, we just happen to have one residing here all the time. It doesn't get a lot of use but is very handy to have. The things are extremely heavy, as you might guess, and when running that thick plate on the bottom vibrates, causing the tamp to well, tamp, and actually move forward. You can barely pull one of these things but when running it moves along on it's on.

It's kinda hard to see in this photo but I left a small turndown around the perimeter of the slab for a footing. You must have this so that the edge of the concrete turns down to contact undisturbed earth. This is kind of a mini version of what we call a monolithic slab. Meaning the slab and footing are poured at the same time. My little footing turndown is only about 5-6 inches wide at the bottom.

I dug the right hand side down just as low as I could, and still have the slab be above grade but that still gave me about 11 inches on the other end. The slab is 12'x8' and it slopes 1/4" per foot in the short direction. This is to allow drainage when I hose the slab off for cleaning. I know most people would not go to the trouble of pouring concrete just for a chicken coop but I have my reasons. 1. I am just partial to concrete; it lasts. You will never have to redo it. 2. No predators will be allowed access to my chickens. They are for my meals, not theirs and I prefer not to kill predators. I think it is better to just not allow them the opportunity. 3. Concrete is easily cleaned and a clean coop is essential. 4. With the rising cost of lumber, concrete is a good deal. The local batch plant used to charge an outrageous minimum on concrete; 5 yards. I suspected with the recent falling economy that maybe they haven't been doing as much business and might have changed their policy. I called them and what do you know? they said they would work me a deal for just 2 yards. How about that? If I have decided to floor the coop in plywood I would have to use pressure treated, probably 3/4 inch, and it would have cost about what 1 yard of concrete is going to run me. With 2 yards, I can also pour a small footing for the tool shed I want to build connected to the coop.
So, I'll be back later to show how I finished my preps for pouring this slab. Oh, and I meant to say I did not buy any lumber to do the formwork. It was all constructed of scrap material I had laying around. Basically just old 2x4's and stuff. Unless it is going to be pretty architectural concrete that is really going to show, I almost never buy form material.

Wednesday, January 05, 2011

All Together Now

Alright, I finally have a completed project to show ya'll. You may remember I started on this one some time back when I first laid this little block knee wall. That was in preparation for this. I backfilled behind the wall with gravel and also filled all the cells of the block with gravel except for the cells in which I had drilled the floor and driven rebar vertically, to help tie the wall to the floor. Those cells I filled with concrete. I then formed this little slab on top of the wall. You will see that I have put a vapor barrier down under the wire. If you ever pour a slab in an area that might ever, ever be enclosed, you need to put a vapor barrier down or you can have moisture issues later. Since this is in an enclosed basement I always put poly down. Say you pour a concrete patio out back and in your wildest fantasies think maybe you might one day make it into a sun room or such; put a vapor barrier down! It is cheap and will save you much if you do ever enclose the area on the slab. This little slab is only two inches thick but will be fine for the shelves I want to put here. I always put wire or rebar or some reinforcing in my slabs also. Welded wire is great and this is some I had scavenged off a job a couple of years ago.

I just happen to have a bit of plyform which I ripped down to make the edge form. Plyform is simply a high grade 3/4" plywood that has been treated with a release agent so that it will not fall apart because it absorbed water off the concrete and will release after the concrete cures without pulling chunks out of the slab edge when you wreck it off. I highly recommend the stuff if you are pouring anything that will show after it is finished. If you can't get it then an alternative is just to spray regular plywood with motor oil. Works great and is much cheaper than painting the plywood with any type sealer.
After establishing the correct elevation for the top of the plyform on one end, I drilled through the plywood, with a hammer drill, into either a concrete filled cell or into the solid wall of the block, as you can see in these photos. With one end of the form set at the correct height, I simply used a 4' level to get the rest of the form correct or you could pull a string line. The top of your block is not going to be correct all the way, so you don't want to just measure up off that.

I then used my cordless drill with a nut driver to run a Tapcon through the plyform and into the block. Tapcons are wonderful! We use the quite a lot at work. They come in a wide variety of sizes and lengths and can be reused many times. Any time you are attaching something to any masonry product and think you might want to take it back off one day, I would recommend using Tapcons. Now, Tapcon is a brand name but anytime you see these big, bright blue screws with coarse threads, that is what they are. You have to have a hammer drill to use them though; a regular drill, even with a masonry bit, won't hardly drill a proper hole for them.

Thank God I was able to borrow Allen's concrete mixer and mixed my mud for the slab. It went SO much easier than mixing by hand. I'm just getting too old for that crap! I just threw a little 2x4 form up in the back and leveled over to establish a grade line on it. You can pop a chalk line and then drive a few nails partially in, along the line, so you can see your grade after the mud goes in. Since the top of my form on front was on grade, I just ran my screed along the top and made sure the other end was on the nails along the 2x4. When you screed concrete, you kinda saw the board back and forth as you push or pull it along. This gives you a pretty level surface; just make sure you stay on your grade marks!
After you screed it off, smooth the surface with a hand float just enough to seal the holes and lay it down smooth. Then leave it alone!! Let the water come to the top but do not work it back in! you will see when the surface starts tightening up. The water will start disappearing. Go over it once more with the float to smooth it further and then let sit again. You can either broom it or go over it with a trowel to get a slicker finish but this takes much practice.

I also ran an edger along the front edge to give it a nice rounded corner on front. I'll get a picture of this thing one day. They are handy to have if you pour much concrete. So, I let the slab cure for about a week and then wrecked the forms and installed my shelving. This frees up much space in the basement and has made things much more organized. I plan to continue the little wall all the way down and probably add a few more shelves. I also bought a few storage tubs and organizers for my tools and drill bits, etc.

I don't really make New Year's resolutions but one thing I really want to work on here is more organization and storage. Getting the basement in proper order is a big accomplishment and I think will help me greatly. It's especially important now because Jack has brought a number of his tools and such and I want to make room for his stuff and have him feel comfortable. Many people have commented that my house was not built for two people but I think I can make it work. We do need a separate workshop but that's a whole 'nuther project!!

Saturday, December 27, 2008

Carved In Stone Part 1


I'm so happy that I finally just bit the bullet and poured my concrete countertop in the bathroom. It was no big deal but I just kept putting it off. Well, I did (and still do) have more pressing exterior issues to deal with but it is nice to have this done. I was actually able to beg a day off from work last week and knock it out. Sunday, Allen set the sink and hooked everything up for me so it was functional for Christmas, which was nice.
Excuse the poor quality of the photos. I almost forgot to even take any and then I was in a hurry so they didn't come out too well.
First, I determined that I wanted the top of countertop to be at 32". Standard height is 30" but that seems low to me. The countertop itself is 2" thick and I used 3/4" material to form the bottom, so I dropped down 2 3/4" to the top of the 2x4's that I attached to the walls to support the "floor" of the form. I ran 3 1/2" screws through the 2x4's into the studs so that makes for strong support and can be easily wrecked. Well, should be. As I mentioned before though, I was in a hurry and not paying attention so I ran a few screws in that could not be gotten to after the concrete was poured and so some of the form just had to be busted to be removed. Even us "pros" make mistakes if we are not thinking.

I found some kind of plastic trim (I think it was for screen doors or something) that made a perfect flexible edge. It bent lengthwise but not widthwise. After I had my 2x4's attached to the wall I scabbed two 1x12's together to make the floor and temporarily attached it in the corner so I could draw out the shape I wanted. I made this base a little oversize and square so I would have plenty of room to draw. I also made a template for my sink shape and placed that on there to help determine the shape of the countertop. I just free handed the shape I wanted for the outer edge with a pencil and then took the base down and cut it with a jigsaw. I glued together 4 small sheets of Dowboard and cut the sink template out of that. the red line you see on the back wall is my grade line. I doweled four #4 bars into the studs in the wall which protrude about 12 " into the slab. I tied a grid within the form out of #3 bars. I had to use slightly thin rebar to get it all within the 2" of mud and the #3 bars are easily bent too. I used lots of construction adhesive on the dowels where they went into the studs. I put 2 dowels in each wall and so that makes a nice perpendicular grid to support the slab once the forms are dropped out.

Here you can see the shoring underneath: the 2x4's on the wall and I cut three 2x's to shore up the outer edge of the form. Even this tiny bit of concrete will be heavy. The countertop has a slight drop to the outer edge. I think about an 1/8" from back to front. I just didn't want any water to run towards the wall and you will never see that slight of a fall. I used 100% silicone to caulk all the cracks where any concrete would be. This prevents a mess from running down the walls when the mud begins to weep and gives you a nice slick finish on the front, bottom edge. The top, front edge I'll have to grind smooth.

Now, I used a mix of one bag of Sackrete to a 1/2 bag of non-shrink grout. Non-shrink grout is mostly portland cement and will help strengthen the mix and I think it helped give it a nicer finish. This is what mud looks like right after it is floated off. I tapped the underside of the form with a hammer to "vibrate" the mud and remove as many air bubbles as possible. You always need to vibrate your concrete in some way. This helps in surround the rebar fully and become as dense as possible. Vibrating also helped the concrete flow down to grade pretty much on its own. Of course, this is such a small amount of concrete it's almost on grade as soon as you get it in the form!

When it is vibrated correctly, this is what it looks like. It gets really wet looking on top and you start seeing these little volcano-looking air pockets pop up. Now, you can vibrate too much but unless you are using the big, mechanical vibrators like we use at work, that is not going to be a problem. I then floated it off one more time to make sure it was on grade and get a little smoother finish. You then just have to let the mud sit and start curing. The more you mess with it, the longer it will take to start setting up because you need to let that water rise up to the surface and start evaporating. And remember, concrete cures, it does not dry. I will show the rest of the process in the next post and the finished product. I think it came out well. If anybody has any questions so far please ask. I know I don't always explain things well.

Monday, February 25, 2008

High Hopes

These photos are a little out of sequence so just bear with me here. I don't have the patience to try to fix them. This is my attempt to fix the problem I am having with rain runoff clouding my spring. Basically, I am trying to build a dirt cricket. A cricket is a small roof that diverts water behind a chimney for those of you who may not be familiar. I discovered 2 holes in the ground on the uphill side of the spring and I believe the muddy water flowing down the hill was then entering the spring underground before it actually reached the mouth of the spring. At least, that is what I am hoping. I hope by backfilling the uphill side it will cause the water to run around the spring and not down these holes or into the mouth of the spring. I put that meter box over the shutoff valve so that it is still accessible, plus the pipe needed to be covered anyway to keep it from freezing.
Here I have backfilled a good bit of the area after putting down a layer of poly as extra protection. I need to lay up another course or two of the stone on the uphill side so that there is a curb of sorts for the water running downhill to be diverted around the spring.
This is the beginning of the project. I got some Sonotube from the job (leftovers) and it was the perfect size! It is 2 feet diameter. Sonotube is great stuff if you need to pour something round. It comes in many different sizes and you can get it at Lowe's or some other similar devil store. Now, in this instance, I poured on the outside of the form where you would normally use Sonotube to pour the inside. Don't laugh at my formwork; it was difficult to get that stuff down in that crevice! And I had to cut the Sonotube open to get it around the water line. Anyway, a few nail pins (also invaluable) and we are ready. I didn't get any photos of the footing but I'm sure you can imagine.
I thought the tube was going to be too big but turns out it was just right to go around the mouth of the spring.
Here I am in my Superwoman pose! I had to haul the concrete and mortar down in a wheelbarrow but the stones I did bring down in my truck. Still, it was a pretty good workout. I kept the Sonotube in place to help me keep a good circle going with the block. When you are through, you just peel the Sonotube off or out of the concrete.
Here you can see the footing and the stone work. Most of the block is some old stuff that I busted up out of the BFA's driveway. I thought it was kind of cool looking because it is so old it was poured back when they used slag from steel mills as the aggregate, so you get these bright, glassy bits in the block. They are pretty much all a uniform thickness too so they lay well. I pointed the outside of the wall on the uphill side to help seal it up and put the poly against the block before backfilling too. So, we'll see. As I said, I need to go a little higher with the wall and build a little berm uphill to help divert more water.
Thank you all for your kind words recently. I am not going to give up on my house. It is just like any construction project; you always run into problems that you did not forsee but you fix them. Everything is just one thing at a time and you keep going. I think I may have not explained my work situation clearly though. I may have to go out of state but we do get to come home about twice a month. Sometimes you can come home every weekend; depends on how far away you are. Anyway, I could make a lot of money if I go and afford to build the other side of the house (much faster) when I come home for good, so it has it's advantages. And if I go with mostly the crew that I have worked with on this last job it will be a hell of a good time. We have already decided that we are going to get up a bowling team and join a league down there and I told the guys we are all going to learn to dance to the Zydeco music too! It will be an adventure for sure.


Wednesday, November 14, 2007

Piggies (Pig's Feet & Snap Ties)

This post may be quite boring to most of you but I have been wanting to put it up for some time now after studying my hits on Site Meter. I get a number of hits for people searching on how to use snap ties and pig's feet etc. and that is a lot of the type of form work we have been doing on this job so I thought it might help some to put up some photos and explain a little. I like doing form work because it is a little like sculpture. The forms themselves can be very artistic, if done well and neatly, with the repetitive elements and shapes. It seems odd to a lot of people to spend so much time building something, sometimes weeks, and then to tear it all back down again.
So, OK, in this photo you can see where we have formed up one side of the wall completely. The whalers (the horizontal 2x4's) and stiff backs (the vertical 2x4's) are all on etc. All those small rods sticking out from the wall are the snap ties. For standard forming you would drill (5/8" hole) your plywood on a 16" grid pattern for the ties. Remember to start 8" off the edges though so that when you butt 2 pieces of plywood together, you have 16" between ties. This works for walls up to 16" thick. Now, there are tons of variations on tie spacing and even using all johnny clamps or all pig's feet but this is the most common method.

Normally, you run 2 johnny clamps, then a stiff back etc. but this can vary too. The johnny clamps hold the whalers and the pig's feet hold the stiff backs. When you get your plywood stood up and nailed off plumb to the rat sill, stick your ties through the holes (short tails for where the clamps go and long tails for the stiff backs) and put your johnny clamps on (loosely fastened). Next, lay your whalers in the clamps. You will have to take your hammer and give them a good whack. Make sure to let enough of them run wild on the ends to lock your corners. You may need to add some temporary bracing now to help the wall stay plumb. Now, stand your stiff backs up. you just sandwich the long tails of the snap ties between two 2x4's and slip the pig's foot on the button of the tie. Tighten the pig's foot down. I usually toe nail the stiff backs on opposite sides at the top and bottom whaler because the pig's feet can loosen up. Some bosses will curse you for this though. Also, alternate the direction of the pig's feet (see photo) and drive an 8 penny nail in that little hole in the foot. This helps hold the stiff backs together also. Generally, you do not nail the stiff backs to one another.
This is a view from on top of the wall looking down into it. Those little cones on the ties hold the plywood a prescribed distance apart. You can sort of see how the tails of the ties are used to hold the hardware. This part of the tie stays in the wall after it is poured. The tails are designed to break off when you wreck the forms, thus the name "snap ties".
This is the wall almost completely done. The carpenter is locking the corners. To do that, you simply lay another, shorter whaler across the ends of the whaler held by clamps and nail it off where they cross. Make sure this whaler is up tight! Two nails at each cross point and make sure that these short whalers run wild also by about 6" as you are now going to add 2 vertical 2x4's in this corner you have just made. This has been done on the left side of the wall. You nail these 2x's in an "L" shape in the corner, 2 nails at each whaler, both sides. The concrete will be pressing outward on the whalers and these corner locks hold the crossed whalers and keep them from moving outward. So, they must all be as tight to one another as possible. This is a very simplified lesson so if I did not explain something clearly, please ask me to clarify. Oh, yeah, after all this you still have to add the turnbuckles and plumb the wall etc. It is easier to do this just after you get the whalers and stiff backs on but before you have everything tightened down and locked off. Generally, every stiff back gets a turnbuckle to get a nice, straight wall.

The house is progressing slowly. I grouted some more this evening but am still not finished with the shower. The house is wearing on me a lot lately. I am having trouble finding a proper control for the ceiling fans. That has been a frustrating ordeal and I guess what I get for ordering industrial fans instead of residential. The house gets invaded everyday by wasps. There are usually 20-30 wasps in the house every time I go down and open up. I have no idea where they are coming from. Everything seems to cost $1,000. The shower, the heat, the siding etc. I seem to keep coming up just slightly short on all my material; tile, grout, paint, plywood. The water is still muddy; I must get another filter. That's another $500.00. I should not complain at all though. So many people have done so much to help me. I've just been working almost every day for over 2 years now to build this house and I'm really getting tired but I just need to suck it up and keep going. It's just one thing at a time.